US Projects





Project Snyder

Project Schedule
Site Identification:   2003
Development Status:   Commissioned
Start of Construction:   November 2006
Commissioning:   December 2007

Basic Data
Installed Capacity:   63 MW
Turbine Type:   21 Vestas V90 – 3.0 MW
Hub Height:   105 m
Rotor Diameter:   90 m

Project Customer
Enel North America, Inc.
Note: WKN developed and constructed Project Snyder, which it sold to Enel in a four week process.



Project Vivaldi

Project Schedule
Start of Development:   2004
Development Status:   Late Stage
Start of Construction:   Projected for 2011
Commissioning:   Projected for 2012



Project Mozart

Project Schedule
Start of Development:   2006
Development Status:   Late Stage
Start of Construction:   Projected for 2011
Commissioning:   Projected for 2012



Project Chopin

Project Schedule
Start of Development:   2009
Development Status:   Mid Stage
Start of Construction:   Projected for 2012
Commissioning:   Projected for 2013



Project Wagner

Project Schedule
Start of Development:   2011
Development Status:   Late Stage
Start of Construction:   Projected for 2011
Commissioning:   Projected for 2012